What a Crane Lift Taught Me That No Certification Did

Writer: Nathan O'Grady
Nathan O'Grady
11 minutes ago
3 min read

I completed my APM PMQ, and it gave me a solid grounding in how to manage a project. It didn't teach me what to do on the day a risk on the register stops being a "risk" and becomes a live problem.

That day came on a project delivering new specialist equipment to a healthcare site.

The setup

Installing equipment like this is never just a delivery. It needs a long list of enabling works first, including a large piece of plant that had to be lifted into position by crane. I was managing the project on behalf of the supplier.

The moment it stopped being theoretical

The original lifting plan turned out not to be viable. The conditions couldn't be signed off as safe for the size of crane we needed, so the plan was dead.

The clock was already running. Equipment like this shouldn't sit unused for long, and every week of delay pushed back its clinical use. When a service is working through a backlog of patients, that isn't just a scheduling inconvenience. It has a real cost for real people.

What I did

I didn't start with a solution. I started with the right people. I set up a call with every stakeholder I could get and asked everyone to throw ideas at the wall.

Some of the ideas were unconventional. We even looked at lifting by air. None of the extreme options were workable, but ruling them out quickly was useful in itself, because it told us where to focus.

The option that survived was also the hardest to organise, because it meant working in one of the busiest parts of a live site. So the next step was an on-site meeting with everyone who would be affected: the lifting team, the mechanical team, construction, traffic management, the client's project manager, and their safety lead. Every logistical problem got dealt with face to face rather than through long email chains.

Then came the decision that made the biggest difference. Rather than wait for the plant to be delivered, we re-planned the programme so the rest of the works could be completed around it. The delivery was now one task with a new date, not a blocker for everything else.

In parallel, I kept the risk register live, got the costs firmed up, and worked to establish what had caused the delay and who owned it. Being clear about that matters, but it only works when the fix is already moving.

The result

The new approach turned out to be a more cost-effective lifting option than the original. Because the cause of the delay was properly understood and owned, the cost wasn't passed on to the client. And because the rest of the works carried on around the delivery, handover slipped by one month rather than several.

What I took from it

Qualifications teach you how to manage a job. They don't teach you how to think when a risk has become reality and everyone is looking at you. Here's what I'd say now:

  • Get the right people together fast. Speed beats perfection in the first 48 hours.

  • Rule options out quickly. Even the impractical ones sharpen your thinking.

  • Keep everything else moving. Don't let one blocked task stop the whole programme.

  • Track the impact, not just the problem. Here it was patient care, not a crane.

  • Agree ownership and cost alongside the fix, not after it.

Comments


Untitled design.png

CONTACT US

Reach out with any
questions or inquiries

ADDRESS

11 Riverside, Riverside Park, Farnham,
Surrey, GU9 7UG, GB,

EMAIL

  • LinkedIn
Untitled design (17).png
bottom of page